Riley Park made ready for its drinking fountain
Early November, 2018, the Water for Riley team faced unexpected issues. The experts tell us that issues during construction projects shouldn’t be unexpected, so let’s go with that wisdom. Since November, those wonderful experts have worked hard to find solutions.
The City of Calgary Parks Department had enough faith in those solutions that we met on site to plot the water line location. On Monday, 3 June, 2019, City staff, Heavy Industries’ Project Manager and Water for Riley met on site, looking at plans and maps.
To be ready for the drinking fountain’s installation, City staff were scheduled to dig and install the water line that will hook up to the three stems of Reflecting Blooms.


Decision on Monday, water line on Tuesday
On Tuesday, 4 June, 2019, the crew showed up with equipment, and Michelle from Parks Department matched the location and the digging to the plans.




Be part of Calgary’s public art legacy;
for Riley Park, for you, and for the future.
Donate to make this vision become reality. At the instructions to seller page, specify that your support is for The Water for Riley Project. The Parks Foundation issues tax receipts for donations greater than $10.00.
We invite everyone to participate as a volunteer, fundraiser, donor, sponsor, or any other role. Call 403 862 1923 and leave your contact information.
See our story in a video http://www.waterforriley.org/2018/07/acad-w4r-video/
One thought on “Installation phase 1: completed”